ABU FATEERA "Z" 400/132/11 KV SUB-STATION

The Ministry of Electricity and Water issued Tender No. 4303 containing the supply and installation of the main transfer station 400/132/11 K.V Abu Fateera area.

Where the tender was awarded to the National Contracting Company as the main contractor and Ali Al Sayegh Contracting Company was approved as a contractor for civil works due to its ability to implement the highest required specifications, considering the time factor for delivery at the times specified by the Ministry.

Indeed, the contract was signed in April 2012 and was implemented with high quality, efficiency, and specifications. Our company proves its ability to implement as required in the most complete manner every time.

As the civil works were completed in June 2014 and the station was handed over as it is ready for operation to the Ministry of Electricity and Water.

This station was commissioned in 2016 and has entered the State of Kuwait public network to serve the Abu Fateera residential area and its environs.

PROJECT NAME : ABU FATEERA "Z" 400/132/11 KV SUB-STATION

LOCATION : KUWAIT - ABU FATEERA

CLIENT : "MEW N.C.C."

NAURATION : CONTRACT NO. MEW/ 4303

DATE OF COMPLATION : 2014

POWER & ENERGY